Energy projects of strategic interest will be authorized on a priority basis

Strategic energy infrastructure projects, developed in partnership with European Union member states, will benefit from a special coordination and authorization mechanism, which will accelerate their implementation. A bill in this regard was voted on by Parliament in the first reading, reports IPN.

The initiative, drafted by the Ministry of Energy, transposes into national legislation the European Union Regulation on guidelines for trans-European energy infrastructures and aims at modernizing the regulatory framework in the energy field. According to the project, the Energy Law will be supplemented with a chapter dedicated to projects of common and mutual interest. This includes the establishment of a special legal regime for strategic energy infrastructure and the introduction of a coordinated and accelerated authorization procedure.

The document establishes the designation of a single point of contact for investors, maximum deadlines for each stage of the authorization process, as well as coordination and monitoring mechanisms between the involved institutions. The authors of the project argue that the new rules will reduce the duration of administrative procedures, will avoid blockages, and will provide more predictability to investments in the energy sector. Currently, the authorization of a common interest energy project takes, on average, about three years, depending on its complexity and the number of involved institutions.

At the same time, the project contains provisions that clarify the application of legislation in the case of energy projects declared of public utility of national interest. The document is to be examined by Parliament in the second reading.



The exhibition “Scent of Warm Bread. Bread in the Iron Age” is inaugurated /National Museum of History of Moldova (July 22 – September 4) / 02:00 PM/.

The exhibition “Urban Archaeology and the Hidden Memory of Chisinau” continues /National Museum of History of Moldova /July 17-November 30/.

The contemporary art exhibition-competition continues: The municipal salon within the “Te salut, Chisinau!” Festival, the VI edition, dedicated to the 590th anniversary of the city /Constantin Brancusi Exhibition Center /July 8-26/.

The documentary exhibition “Echo from the past, for present and future” continues, dedicated to the memory of the victims of Stalinist deportations and one of the most tragic episodes in the history of Bessarabia /BNRM /July 3-August 3/.

The exhibition “The Thread of Identity! The traditional Romanian costume in book illustrations made by plastic artists from the Republic of Moldova” continues /BNRM /June 25-August 15/.

The graphic exhibition by Lica Sainciuc continues, opened as part of the Creative Industries Festival /Lutnita Gallery /June 5 – July 31/.

0 FacebookTwitterPinterestEmail


Energy projects of strategic interest will be authorized on a priority basis

Strategic energy infrastructure projects, developed in partnership with European Union member states, will benefit from a special coordination and authorization mechanism, which will accelerate their implementation. A bill in this regard was voted on by Parliament in the first reading, reports IPN.

The initiative, drafted by the Ministry of Energy, transposes into national legislation the European Union Regulation on guidelines for trans-European energy infrastructures and aims at modernizing the regulatory framework in the energy field. According to the project, the Energy Law will be supplemented with a chapter dedicated to projects of common and mutual interest. This includes the establishment of a special legal regime for strategic energy infrastructure and the introduction of a coordinated and accelerated authorization procedure.

The document establishes the designation of a single point of contact for investors, maximum deadlines for each stage of the authorization process, as well as coordination and monitoring mechanisms between the involved institutions. The authors of the project argue that the new rules will reduce the duration of administrative procedures, will avoid blockages, and will provide more predictability to investments in the energy sector. Currently, the authorization of a common interest energy project takes, on average, about three years, depending on its complexity and the number of involved institutions.

At the same time, the project contains provisions that clarify the application of legislation in the case of energy projects declared of public utility of national interest. The document is to be examined by Parliament in the second reading.


Children from the diaspora aged 7 to 12 will have the opportunity to discover Chisinau through a series of free educational and creative activities. From August 10 to 15, they will take part in tours of the capital, meetings with writers, and creative workshops organized by the “B. P. Hasdeu” Municipal Library under the auspices of the Chisinau City Hall, according to IPN.

Representatives of the institution note that the “At Home in Chisinau” summer camp offers a captivating journey into the city’s history and culture. Over the course of six days, children will explore iconic sites in the capital and discover legends and stories about Chisinau. The program also includes meetings with artisans, artistic activities, and traditional games.

With the exception of guided tours, all activities will take place at the main branch of the “B.P. Hasdeu” Municipal Library. Registration for the summer camp is open until August 7 and can be completed by filling out the online form.

The first edition, which took place online, was attended by 20 children from Germany, Italy, France, and Ireland.

0 FacebookTwitterPinterestEmail




1 IANUARIE, 2025
1 IANUARIE, 2025