Over 260 MW released into the network for renewable energy projects

Over 260 MW of grid connection capacity, intended for renewable energy power plants, become available to investors, after the National Agency for Energy Regulation applied the non-utilization fee for expired and unused connection permits. The measure targets capacities that had been reserved in the network, without the projects being implemented, reports IPN.

The Administration Council of ANRE has adopted nine resolutions regarding the application of this tax, the total value exceeding 131 million lei. The approvals were issued for eight photovoltaic power plant projects and one wind farm project, with a total capacity of 262.45 MW. According to ANRE, the capacity was reserved in the network without being used for the implementation of real investments.

The introduction of the non-valorization tax and the performance bond was initiated last year by the Ministry of Energy, to hold accountable the holders of connection permits. The measure was adopted in the context where some of the permits were obtained without the projects being completed within the established deadlines, which limited the access of other energy initiatives to the network.

In accordance with the legislation, the holders of permits who have not voluntarily renounced them by June 30, 2025 and have not implemented the projects will pay, upon the expiration of the permits, a fee between 50% and 70% of the value of the financial guarantee for good execution. For permits issued after this date, the financial guarantee is mandatory when obtaining the permit, and in the absence of the power plant being built, the sum will be retained by the network operator for maintenance and infrastructure development.



The city of Chisinau hosts the XIth edition of the international sports festival “Golden Bull” (23-26 July) /Athletics Manege /at 10:30 AM/.

The Popular Assembly of Gagauzia, in collaboration with the Constitutional Justice Institute, is organizing an international scientific-practical conference on the topic: “Adherence to constitutional norms in the Republic of Moldova – a test for the rule of law” /Cultural House of the city of Comrat /at 11:00 AM/.

Elderly people from the capital are invited to a new edition of musical performances, held within the framework of the socio-cultural weekend project “Dialogue between generations” (July 25-26) /Public Garden “Stefan cel Mare si Sfant” /at 04:00 PM/.

The citywide chess and checkers championship for seniors is taking place in the sectors of the capital /25-26 July/.

The City Hall of Chisinau organizes fairs and markets with local products and goods in the sectors of the capital /25-26 July/.

0 FacebookTwitterPinterestEmail


Over 260 MW released into the network for renewable energy projects

Over 260 MW of grid connection capacity, intended for renewable energy power plants, become available to investors, after the National Agency for Energy Regulation applied the non-utilization fee for expired and unused connection permits. The measure targets capacities that had been reserved in the network, without the projects being implemented, reports IPN.

The Administration Council of ANRE has adopted nine resolutions regarding the application of this tax, the total value exceeding 131 million lei. The approvals were issued for eight photovoltaic power plant projects and one wind farm project, with a total capacity of 262.45 MW. According to ANRE, the capacity was reserved in the network without being used for the implementation of real investments.

The introduction of the non-valorization tax and the performance bond was initiated last year by the Ministry of Energy, to hold accountable the holders of connection permits. The measure was adopted in the context where some of the permits were obtained without the projects being completed within the established deadlines, which limited the access of other energy initiatives to the network.

In accordance with the legislation, the holders of permits who have not voluntarily renounced them by June 30, 2025 and have not implemented the projects will pay, upon the expiration of the permits, a fee between 50% and 70% of the value of the financial guarantee for good execution. For permits issued after this date, the financial guarantee is mandatory when obtaining the permit, and in the absence of the power plant being built, the sum will be retained by the network operator for maintenance and infrastructure development.


The “Eugen Doga” International Airport in Chisinau has launched a public tender for the current repair and maintenance of the asphalt concrete surfaces of the aerodrome platform. The estimated value of the contract is 67.2 million lei, excluding VAT, reports IPN.

According to the announcement published on the public procurement platform, bids can be submitted during the period of August 3-17, after the clarification request stage has ended, which will take place until August 3.

According to the technical documentation, a large part of the investment is intended for the repair of platform no. 1, where the aircraft parking spots are located. The verified estimate for these works is approximately 55 million lei, including VAT.

The repairs are not limited to the area where the aircraft are stationed, but also target the infrastructure used daily by airport services. Thus, the repairs also include the connection area between the control point and the aerodrome platform, the parking area designated for airport vehicles, the area where the workshops and material depots are located, as well as the area of the fuel supply station. At the same time, work will also be carried out on the access road to the passenger terminal.

The specification book indicates that the need for interventions was identified following technical inspections. The documentation further stipulates that the interventions will be carried out in operational areas and with restricted access, without affecting the airport’s activity.

0 FacebookTwitterPinterestEmail




1 IANUARIE, 2025
1 IANUARIE, 2025